12/3/2002 - 12/5/2002
FAM Information Workshop, Reno NV
Wildland Computer-Aided Dispatch -- WildCAD
Aaron Gelobter
- History of the WildCAD system
- Started with DOS-based CAD (CAD/CAN) system and eventually added multi-users, GIS, and Relational Database
- Uses a standard hardware platform
- Created for use in simple to complex interagency centers
- Testing
- Central California Interagency Communication Center (Porterville, CA)
- FS, BLM, BIA, extensive state and local Cooperating Agencies
- 1997 initial contract issued
- 1998 beta test completed
- 1999 Twelve additional centers added
- 1999 Region 5 FS/BLM
- 2000 Nevada BLM and FS Joint Centers
- 2001 BLM in UT, ID, WY and FS region 4
- 2002 FS Region 2 and NICC
- 2003 BLM in AZ, NM
- Milestones
- 37 centers across the country (100 to 14,000 incidents per year)
- 12 Centers Scheduled for 2003
- 300,000 incidents to date handled by WildCAD
- BLM National Implementation Site License (up to 100 additional centers)
- Charted User Committee and Board of Directors
- The WildCAD system is currently in use on 28 national forests and all BLM Field offices (22 currently online)
- WildCAD Training
- New Centers
- Three 2 day training sessions from the vendor
- Onsite installation and training
- Dispatcher and System Administrator Training
- Annual System Administrator Conference
- WildCAD Priorities
- Support to existing online centers
- BLM National Implementation
- Enhancements
- Additional Centers
- WildCAD Contract
- 5 year middle of year 4
- provides full Technical Support
- Annual Enhancements
- Copy of the Source Code is stored "In Escrow"
- New 5 year contract (FY 03-07)
- WildCAD Board of Directors - WildBOD
- Review recommendations
- Identify concerns
- Develop request for Technical Approval
- Identify and strive towards common business practices that will be applied to the program